News

Chinese contractors abandon Vietnam hydro project as tensions remain high

A major hydropower project in Vietnam stood in limbo over the weekend amid reports that the two Chinese contractors building it have abandoned the project and returned home after failing to secure extra funding.

Dormant equipment and unused materials now dominate the site of the $270m Thuong Kon Tum hydropower project in Kon Tum Province, which has been abandoned, according to a Vietnamese newspaper, by joint venture partners Hydrochina Huadong Engineering Corporation and China Railway Construction Co Ltd., who won the construction contract in 2009.

The Chinese contractors appeared deliberately stubborn regardless of the good will from Vietnam– Vo Thanh Trung, general director of the project’s investor

The plant was designed to produce 1.09 million kWh a year and to be operating at full capacity by the end of this year, but work has been severely delayed and the contractors had been refused their requests for additional funds, the newspaper, Tuoi Tre, reported.

The scenario built by the Vietnamese newspaper is that the Chinese firms were unable to complete the work on time for the agreed price.

After progress milestones were not met, the contractors reportedly asked for more money. The newspaper quotes Vo Thanh Trung, general director of the project’s investor, Vinh Son-Song Hinh Hydropower JSC (VSH), as saying they "continued asking for unreasonable conditions".

The VSH chief said the Chinese contractors asked for a sum of $37.65m that was not included in the contract and on 25 May threatened to halt construction if the funds were not released.

"When they could not explain the rationale behind the requests, the Chinese contractors appeared deliberately stubborn regardless of the good will from Vietnam," Trung told Tuoi Tre.

Tuoi Tre also reported that the Chinese firms had complained that Vietnamese workers quit work and that the site was not secure, claims that VSH and local police denied, Tuoi Tre said.

The project difficulties come as tensions are high between Vietnam and its much larger neighbour. Anti-Chinese protests erupted after China stationed an oil rig in disputed waters in May. A Chinese vessel reportedly rammed a smaller Vietnamese one, which sank, in the vicinity of the rig. The rig was withdrawn in July but in Vietnam factories have been destroyed in rioting and four workers have been killed.

Economically, China dominates its Communist neighbour, and Chinese contractors are believed to hold a major share of Vietnam’s construction and infrastructure projects. Le Hong Hiep, of Vietnam National University, told The Economist that that share will shrink as Vietnamese clients look elsewhere.

Meanwhile, Vietnam Electricity (EVN), the country’s state-run power company that holds a 30% stake in the project, said that a "more capable" contractor, possibly from Germany or France, would be found if the Chinese joint venture does not return to complete the work.

"Otherwise, Vietnam will select another contractor and impose fines on the Chinese firms as per the contract," EVN’s deputy general director, Nguyen Tai Anh, told Tuoi Tre on Friday.

VHS and the Chinese contractors are scheduled for renegotiation meetings this week, the newspaper said.

Story for GCR? Get in touch via email: [email protected]

Latest articles in News